2002

September: Meeting with Dr. Driessen to determine project scope.

October: Single channel board completed.

November: Began circuit schematic design.

December: Circuit schematic completed, Began PCB layout.


2003

January: PCB layout is completed.

February: PCB boards returned, Parts ordered, Began PCB assembly.

March: Debugging. The 499 project was presented on March28th.

April: The Final Report handed in and the Website completed on the April 5, 2003.